(1) Except as provided in paragraph (2), each report under subsection (e) with respect to a major defense acquisition program shall include the following:
(A) The name of the major defense acquisition program.
(B) The date of the preparation of the report.
(C) The program phase as of the date of the preparation of the report.
(D) The estimate of the program acquisition cost for the program (and for each designated major subprogram under the program) as shown in the Selected Acquisition Report in which the program or subprogram was first included, expressed in constant base-year dollars and in current dollars.
(E) The current program acquisition cost for the program (and for each designated major subprogram under the program) in constant base-year dollars and in current dollars.
(F) A statement of the reasons for any increase in program acquisition unit cost or procurement unit cost for the program (or for any designated major subprogram under the program).
(G) The completion status of the program and each designated major subprogram under the program
(i) expressed as the percentage that the number of years for which funds have been appropriated for the program or subprogram is of the number of years for which it is planned that funds will be appropriated for the program or subprogram, and
(ii) expressed as the percentage that the amount of funds that have been appropriated for the program or subprogram is of the total amount of funds which it is planned will be appropriated for the program or subprogram.
(H) The fiscal year in which information on the program and each designated major subprogram under the program was first included in a Selected Acquisition Report (referred to in this paragraph as the base year) and the date of that Selected Acquisition Report in which information on the program or subprogram was first included.
(I) The type of the Baseline Estimate that was included in the baseline description under section
2435 of this title and the date of the Baseline Estimate.
(J) The current change and the total change, in dollars and expressed as a percentage, in the program acquisition unit cost for the program (or for each designated major subprogram under the program), stated both in constant base-year dollars and in current dollars.
(K) The current change and the total change, in dollars and expressed as a percentage, in the procurement unit cost for the program (or for each designated major subprogram under the program), stated both in constant base-year dollars and in current dollars and the procurement unit cost for the program (or for each designated major subprogram under the program) for the succeeding fiscal year expressed in constant base-year dollars and in current year dollars.
(L) The quantity of end items to be acquired under the program and the current change and total change, if any, in that quantity.
(M) The identities of the military and civilian officers responsible for program management and cost control of the program.
(N) The action taken and proposed to be taken to control future cost growth of the program.
(O) Any changes made in the performance or schedule milestones of the program and the extent to which such changes have contributed to the increase in program acquisition unit cost or procurement unit cost for the program (or for any designated major subprogram under the program).
(P) The following contract performance assessment information with respect to each major contract under the program or subprogram:
(i) The name of the contractor.
(ii) The phase that the contract is in at the time of the preparation of the report.
(iii) The percentage of work under the contract that has been completed.
(iv) Any current change and the total change, in dollars and expressed as a percentage, in the contract cost.
(v) The percentage by which the contract is currently ahead of or behind schedule.
(vi) A narrative providing a summary explanation of the most significant occurrences, including cost and schedule variances under major contracts of the program and any designated major subprogram under the program, contributing to the changes identified and a discussion of the effect these occurrences will have on future program costs and the program schedule.
(Q) In any case in which one or more problems with the software component of the program or any designated major subprogram under the program significantly contributed to the increase in program unit costs, the action taken and proposed to be taken to solve such problems.